The modernization of the baby food manufacturing plant included the reconstruction and extension of C1 and C2 production and storage buildings together with their office and staff parts, as well as combining them into one C1C2 complex. As part of the task, earthworks, necessary demolitions, reconstruction and extension were carried out, mechanical and electrical systems were installed, and the paved surface for the new complex was expanded. The task included also the installation of industrial systems, including a process cold water system with a cleaning system, a steam and condensate system as well as a compressed air system. After the reconstruction, the entire C1C2 complex has 7 floors (it is 33.7 m tall at the highest point).

Due to the intended use of the complex, its significant part was constructed in accordance with the requirements of the Hazard Analysis and Critical Control Points (HACCP) system.

Nutricia / Opole

Client: Nutricia
Execution period: 2004-2005
Scope of work: general repair and extension works
Location: Opole, Marka z Jemielnicy 1 St.
Total area: 11,400 m²