The expansion of the production plant for assembly units as well as stamped and formed parts, with a production and warehouse part (4,674 m²), an office and staff part (250 m²), a chemical warehouse and a lock building (120 m²). The total area of the expanded part was 5,100 m2. Kajima prepared an executive design and completed all earthworks as well as installation and finishing works. Kajima was also responsible for the construction of this plant in 2005.

Haerter, expansion / Legnica

Client: Haerter Technika Wytłaczania
Execution period: 2007
Scope of work: execution design, general contracting
Location: Legnica, Jaworzyńska 291 St.
Total area: 5,100 m²