The extension of the chocolate production plant included the relocation of the existing sewer networks and process systems from the area of the planned extension, construction of a production and administration building (production: 16,000 m², offices: 3,200 m²), chocolate tank building (approx. 300 m²), storage part (500 m²) and smaller technical buildings (pumping station, chiller building), as well as the construction of new infrastructure (rainwater discharge, fire protection, water supply, processes, gas supply, roads and external squares) and landscaping. Kajima’s tasks did not include electrical works. For maintaining a high standard of occupational health and safety during the construction Kajima was awarded a distinction in the Safe Construction competition (organizer: National Labor Inspectorate)

Cadbury Wedel / Wrocław

Client: Cadbury Wedel
Execution period: 2008-2009
Scope of work: execution design (construction section), main subcontracting
Location: Bielany Wrocławskie, Czekoladowa 1 St.
Total area: 19,600 m²