Extension of a production and office building for the coating production line of the 3M production plant. The contractor’s task was to adapt the existing building to introduce and launch a new production line. The works were carried out during the operation of the plant, in a manner that did not interfere with its functioning.

The first stage was to perform static analyses of the structure in terms of expansion, superstructure and placement of new production machines, as well as a detailed design for all necessary industries. Then the construction of the existing part was strengthened, foundations for future machines and superstructure were made. The main part of the project was the execution of installations (including process installations). At the end, installation connections to process machines were made.

3M, extension / Wrocław

Client: 3M Wrocław
Execution period: 2018
Scope of work: execution design, general contracting
Location: Wrocław, Kowalska 143 St.
Total area: 2900 m²